Beta closed Monday — notification opt-out issue is scoped and in the next build. Compliance disclosure is the real gating item: Risk Lead review was pushed from last week and is now on the critical path into store submission. Rails dependency still floating; if cutover doesn't confirm this week, the GA date needs to move. Accessibility violations need Design Lead to move fast — three AA findings are a store-rejection risk.
Parallel run is the good news — 8 days, no critical failures. The blocker is compliance review scheduling: Risk Lead deprioritized it last sprint and it's now on the critical path for two programs simultaneously. Edge-case transaction validation is scoped and assigned; should close before the cutover window. Rollback playbook needs one more sign-off pass from Eng Lead.
Mostly on track. Partner API test run Friday surfaced 2 issues — partner has them, fix expected this week. Comms approval is the scheduling risk: 14-day window before go-live means Marketing Lead must approve by Thursday latest. CS training starts next week and is on track. Accrual logic on staging, QA sign-off expected Wednesday.